Sullivan Center Construction Update

October 26, 2016

Construction crews are busy at the Sullivan Community Center completing exterior projects.  Within the next couple weeks, the following projects will be complete:

  1. The exterior site work including sidewalks, curbs, paths, and parking lot restoration.
  2. The outdoor playground including the synthetic turf surface and a fenced, secure yard.
  3. The roof on the preschool wing is complete.  Window installation in addition to interior framing and drywall will begin.
  4. The gymnasium roof is complete.  The interior gym walls will begin drywall installation.